Minimum Stock and Reorder Point: When Should a Purchase Request Open?
Open a purchase request not when stock “runs out” but when the inventory position falls to the reorder point. Inventory position = on hand + open orders due on time − reserved. Reorder point = average daily usage × actual lead time + safety stock. A sheet watching only stock on hand reorders items already on the way and counts overdue orders as “coming”. Below I cover formulas, measurement, an Excel setup and its limits, using one quarter in a 408-item warehouse. The company, codes and all numbers are fictional.
What do reorder point, safety stock and min/max mean?
The reorder point (ROP) is usage until delivery plus safety stock; an order opened there should arrive before safety stock runs out.
- Average daily usage: Issues in the last 91 days (13 weeks) ÷ 91. Use calendar days, and measure lead time in them too. Mixing them skews the ROP: calendar-day usage with working-day lead time shrinks it, the reverse inflates it.
- Lead time: The actual days from order date to goods receipt, not the quoted time.
- Min / max: Min opens an order; in the old sheet a hand-typed number, here the ROP. Manual Min is a floor the ROP cannot drop below. Max is what an order fills up to: ROP + daily usage × cover days (days of usage one order covers).
- Order quantity: Max − position, never below the supplier’s minimum order quantity (MOQ), rounded up to the pack multiple.
How is safety stock calculated?
I suggest starting simple: safety stock = average daily usage × (longest actual lead time − average lead time). It covers the worst delay seen, not a usage spike; a starting suggestion, not a standard coefficient.
The statistical route adds usage variability. With a fixed lead time, safety stock = z × standard deviation of usage × √lead time; z comes from the service level; Excel’s NORM.S.INV(0.95) gives 1.645 for 95%. If lead time varies too, its deviation enters the formula (Wikipedia: Safety stock; the article cites Chopra et al. for the variable-lead-time formula only). A weekly deviation needs lead time in weeks.
RZ-220 heater band: weekly standard deviation 1.38 units over 13 weeks, lead time 2 weeks. At 95%, 1.645 × 1.38 × √2 ≈ 3.2, rounded up to 4; the simple route gave 3. For rare, irregular items statistics swing; start simple, compare after a quarter.
A worked example: one quarter in a 408-item warehouse
A plastic injection moulding plant’s maintenance and packaging store holds 408 items: 142 spare parts (38 critical: a machine stops when one fails), 156 consumables and 110 packaging items. Stock is in Excel with a hand-typed “Min” per row; open orders sit in the buyer’s own list. Orders go out when a row turns red or production says “it’s gone”.
In one quarter (13 weeks):
- 23 stockouts, 5 of which stopped a machine. All five were critical spares.
- 9 duplicate orders: Below Min, a second order went out while the first was on the way.
- 61 of 214 items ordered averaged longer actual lead times than Excel assumed; 44 from just four suppliers.
- 97 items had no issues for 13 weeks; 31 are critical spares.
What if orders had opened at the ROP? I calculated each event in a script:
| Cause of the stockout | Events | Machine stops | ROP alert in time? |
|---|---|---|---|
| Ordered only when “it’s gone” | 11 | 1 | Yes, all 11 |
| Min built on a short planned lead time | 6 | 2 | Yes, all 6 |
| New item, before its first issue | 3 | 0 | No (no Manual Min) |
| Bulk issue during a mould breakdown | 2 | 1 | No |
| Supplier 17 days later than expected | 1 | 1 | No |
The estimate is optimistic: the alert is acted on the same day and lead time never exceeds the supplier’s longest seen; the 17-day delay falls outside that. The alert would have caught 17 of 23 events and 3 of 5 machine stops, and prevented all 9 duplicate orders. In the other 6 the formula is helpless: before a first issue, and without a Manual Min, there is no number; no average foresees breakdown usage; safety stock built on the longest lead time seen cannot cover a 17-day delay. There the sheet can only show the delay the day the date passes.
Why is inventory position different from stock on hand?
Inventory position = on hand + open orders − reserved. Reserved means allocated to a work or sales order, not yet issued; see reserved stock tracking.
Open orders mislead both ways:
- Ignore them and you double order: RZ-220 has 6 on the shelf against an Excel Min of 8, so the sheet says “order”. But 10 arrive in 6 days and 2 are allocated to maintenance: position 6 + 10 − 2 = 14, above the ROP of 10.
- Count them blindly and you hide a delay: KA-12 mould release spray has 30 cans; a 96-can order is 4 days overdue. Counted, the position is 126 and no alert appears. My suggested rule: an overdue order leaves the position for an “Overdue” column until the supplier gives a new date and the sheet is updated. KA-12 falls to 30, below the ROP of 48: “Chase overdue first”. If the supplier confirms a date 5 days out, the position returns to 126 and no order opens.
With several warehouses, calculate the position per warehouse.
How do you estimate usage?
For regular movers, the 13-week average is enough. Four cases need their own rule:
- Items tied to the production plan: Cartons, bags and stretch film follow the coming weeks’ plan (planned units × packaging per unit).
- New items: NZ-08 nozzle tip was set up 24 days ago and 14 have been issued. Divided by 91, the ROP is 5; by the 24 days since setup, 16. With 9 on the shelf, only the second alerts. Early on, enter a Manual Min from a similar item.
- Items with no movement: The formula returns 0. For a critical spare (TK-J thermocouple) that means no alert until zero. The maintenance lead enters a Manual Min; the example’s 31 items are this kind.
- One-off bulk issues: A mould breakdown inflates the average. Record it with Type “Breakdown”; the Usage formula sums only “Issue”.
How do you measure lead time?
Record lead time on every delivery as days from order to receipt and average it per supplier; deliveries per item are too few.
Excel said 10 days for T-04 (heater bands and thermocouples). The last six deliveries took 12, 14, 11, 19, 13 and 15 days: average 14, longest 19, all six above plan. A ROP built on 10 days has eaten its safety stock before goods arrive. With 44 of the 61 late items from four suppliers, purchasing talks to those four first.
For partial deliveries, measure to the last part’s receipt.
Excel setup: three tables and one alert column
Three Excel Tables are enough. Formulas use English names and commas.
- Movements: Date · Code · Type (Receipt, Issue, Breakdown, Count) · Qty. On hand comes from this table; see the Excel inventory tracking template.
- Orders: Order No · Code · Supplier · Order Date · Expected · Qty · Received · Receipt Date · Status · Remaining · Lead Days.
- Items: Code · Group · Supplier · Setup Date · Plan Lead · Manual Min · Cover · MOQ · Pack · Reserved, then the formula columns.
Two formulas in Orders:
Remaining: =IF([@Status]="Cancelled",0,MAX(0,[@Qty]-[@Received]))
Lead Days: =IF([@[Receipt Date]]="","",[@[Receipt Date]]-[@[Order Date]])
Formula columns in Items:
On Hand: =SUMIFS(Movements[Qty],Movements[Code],[@Code],Movements[Type],"Receipt")-SUMIFS(Movements[Qty],Movements[Code],[@Code],Movements[Type],"Issue")-SUMIFS(Movements[Qty],Movements[Code],[@Code],Movements[Type],"Breakdown")+SUMIFS(Movements[Qty],Movements[Code],[@Code],Movements[Type],"Count")
Usage: =SUMIFS(Movements[Qty],Movements[Code],[@Code],Movements[Type],"Issue",Movements[Date],">"&TODAY()-91)
Daily: =[@Usage]/MAX(1,MIN(91,TODAY()-[@[Setup Date]]))
Lead: =IFERROR(AVERAGEIFS(Orders[Lead Days],Orders[Supplier],[@Supplier],Orders[Lead Days],">0"),[@[Plan Lead]])
Longest: =MAXIFS(Orders[Lead Days],Orders[Supplier],[@Supplier])
Safety: =ROUNDUP([@Daily]*MAX(0,[@Longest]-[@Lead]),0)
ROP: =MAX([@[Manual Min]],ROUNDUP([@Daily]*[@Lead]+[@Safety],0))
Max: =[@ROP]+MAX(1,ROUNDUP([@Daily]*[@Cover],0))
Open: =SUMIFS(Orders[Remaining],Orders[Code],[@Code],Orders[Expected],">="&TODAY())
Overdue: =SUMIFS(Orders[Remaining],Orders[Code],[@Code],Orders[Expected],"<"&TODAY())
Position: =[@[On Hand]]+[@Open]-[@Reserved]
Alert: =IF([@Position]<=[@ROP],IF([@Overdue]>0,"Chase overdue first","Order now"),IF([@Overdue]>0,"Chase overdue",""))
Suggested: =IF([@Position]<=[@ROP],CEILING(MAX([@MOQ],[@Max]-[@Position]),[@Pack]),0)
Notes on the formulas:
">"&TODAY()-91covers exactly 91 days including today.MAX(1,…)keeps Max above the ROP for an item with zero daily usage; otherwise an item already on order keeps alerting.- A Count row holds the count difference (can be negative). Enter a receipt twice, in Movements and in Orders; skipping either breaks the position.
">0"keeps blank Lead Days out of the average. With no deliveries,IFERRORuses Plan Lead, Longest returns 0, safety stock is 0.MAXIFSexists in Excel 2019 and later (Windows and Mac), not 2016 (Microsoft: MAXIFS). In 2016, enter=MAX(IF(Orders[Supplier]=[@Supplier],Orders[Lead Days],0))with Ctrl+Shift+Enter.CEILINGrounds up to a multiple of its second argument (Microsoft: CEILING). Require a Pack of at least 1 with data validation. If the MOQ exceeds the pack, the result meets both.- In
SUMIFSthe sum range comes first (Microsoft: SUMIFS). Make Expected mandatory with data validation.
Results for the five example items:
| Item | Daily · Lead/Longest | Safety · ROP · Max | Position → result |
|---|---|---|---|
| RZ-220 heater band | 0.44 · 14/19 | 3 · 10 · 37 | 6 + 10 − 2 = 14 → no alert |
| KL-410 carton | 200 · 7/10 | 600 · 2,000 · 8,000 | 1,850 → order now, 6,250 |
| KA-12 spray | 3 · 12/16 | 12 · 48 · 138 | 30 (96 overdue) → chase overdue first, 108 |
| TK-J thermocouple | 0 · 14/19 | 0 · 2 (Manual Min) · 3 | 1 → order now, 2 |
| NZ-08 nozzle tip | 0.58 · 18/25 | 5 · 16 · 51 | 9 → order now, 42 |
KL-410: max − position is 6,150, above the MOQ of 1,000; rounded to packs of 250, 6,250. A position equal to the ROP also alerts.
How much effort does each item deserve?
Not every item needs equal care. Does a machine stop when the item runs out? If so, even a cheap, idle spare needs a Manual Min and frequent counts; zero from the formula is not enough. Split the rest by annual usage value into A, B, C; review A weekly and C monthly, with boundaries set for your company.
When should threshold tracking leave the spreadsheet?
The deciding question: does one person keep all three parts of the position current? Then a spreadsheet is enough. If stores, purchasing and maintenance each enter their part, the sheet is right only when everyone updates on time.
| Route | When | Limit |
|---|---|---|
| Manual Min column | Few items, one person, short lead times | Open orders invisible; duplicates, late notice |
| Three-table Excel setup | A few hundred items, one or two people | Manual dates and receipts; late updates give wrong alerts |
| ERP reorder feature | Stock and purchasing already in the ERP | Typed-in lead times need the same measuring |
| Custom web application | Stores, purchasing, maintenance are separate; many critical spares | Unrecorded issues break it too |
When you do not need an application: A few dozen items, one warehouse, one person for stock and orders: the formulas suffice. If your ERP calculates a reorder point, update its lead time and safety stock with actual values first; a second sheet beside it creates two truths.
How would alerts work in the application to be built?
It can be built to your needs, and the scope is set in writing at the first step. Functions that could be developed for the example plant:
- Stores record issues against a work order or machine; breakdown issues stay out of the average.
- Purchasing sees the position’s three parts and the suggested quantity in the alert list and opens requests there; a second request for the same item triggers a warning.
- Overdue orders move to the “Overdue” list and purchasing is notified (we choose the channel together at the first step).
- Recording a receipt writes the lead time automatically.
- The maintenance lead sets Manual Min for critical spares, a manager sets cover days; every change is logged with old and new values.
AI could read a new date from a supplier email (“shipping next week”) and suggest it for Expected; nothing changes until purchasing approves. Quantities and ROP come from the rules above, not the model. Reading stock from or writing requests to an ERP is assessed as part of the scope.
It runs on a VPS that can be opened in your company’s name; records are yours and export to Excel or CSV anytime. Small and medium-sized teams pay no per-user licence; the cost is server and maintenance. Source code sits in a repository you can access, with run instructions, dependencies and known limits. General approach: custom web apps for your team.
The first meeting is paid. On the contact page, tell me your item count, last quarter’s stockouts and where open orders are kept today.
What I have not verified
I read the sources on 2026-11-01.
- I did not run the formulas in Excel or Google Sheets; I tested their logic and every example number in Python.
- I could not find what
CEILINGreturns for a significance of 0; hence the Pack validation. - I did not test blank Expected or Lead Days cells against the criteria; that a blank-Expected row lands in neither Open nor Overdue is my inference.
- I took the statistical formulas from the encyclopaedia article, not the paper.
Frequently Asked Questions
What if the supplier’s minimum order quantity exceeds my monthly usage?
The formula applies the minimum; the problem is stock sitting for months. Ask for a blanket order with split deliveries; each delivery is its own Orders row with its own expected date.
Does a count difference change the reorder point?
The ROP does not; the position does. A short count lowers on hand and may trigger the alert at once. A shortfall repeating every count means unrecorded issues; usage, and so the ROP, comes out too low.
Do the thresholds shift every day?
Yes, TODAY() shifts the window daily, slightly for regular items. For a fixed weekly list, use a Cutoff date cell updated weekly instead.
How do I work?
Work-hour packages
Tell me about your business and what you need on WhatsApp or by phone; we agree on a work block of somewhere between 5 and 40 hours and I start doing what is needed. What you get is not a calendar window — it is net working hours spent directly on your business. I can use 40 hours working three days straight, or deliberately spread it out and finish it over a year — whatever the work calls for. I do not spend my time estimating how long something will take, I spend it doing the work; every hour I spend leaves a lasting result in your business. We keep going for as long as you find it useful.
Why not monthly?
Is 40 hours a week?
On a fixed monthly fee both sides are watching the wrong thing: you watch a fixed cost, the other side watches how many more contracts like this they can line up. Working by the hour puts us both in front of the same thing — the real value of the work that got done. I know not having an upfront answer to "how much will this cost in total?" is the natural cost of this model. But instead of paying a fixed fee for months to a setup that is not producing results, you only pay for the qualified time spent on your work — and you see exactly where that time went, start to finish. That is why my clients keep coming back.
